| [1] |
Description Of Project
& Name Of Client |
Construction of Factory Building for M/s. SE Forge Ltd., Vaghodia - Vadodara. |
| Value Rs. Lakhs |
1791* |
| Date Of Commencement |
Oct. 2007 |
| Scheduled Completion Date |
Jun. 2008 |
| % of Completion |
72% |
| Consultant Architect |
C. R. Narayan Rao, Chennai
|

|
|
|
| |
| [2] |
Description Of Project
& Name Of Client |
Construction of Factory Building for M/s. Lathia Rubber Manufacturing Company Pvt. Ltd., Pardi -Vapi
|
| Value Rs. Lakhs |
350* |
| Date Of Commencement |
May. 2007 |
| Scheduled Completion Date |
May. 2008 |
| % of Completion |
95% |
| Consultant Architect |
M/s. Clancy Global Consulting Engineers, Mumbai. |
|
|
|
| |
| [3] |
Description Of Project
& Name Of Client |
Construction of Compressor Station For Reliance Gas Industries Ltd. - Valsad. |
| Value Rs. Lakhs |
1750 |
| Date Of Commencement |
Mar. 2007 |
| Scheduled Completion Date |
May 2008 |
| % of Completion |
90% |
| Consultant Architect |
-- |
|
|
|
| |
| [4] |
Description Of Project
& Name Of Client |
Construction of Process House for M/s. Mudra Lifestyle Ltd., Boisar |
| Value Rs. Lakhs |
670* |
| Date Of Commencement |
Feb. 2008 |
| Scheduled Completion Date |
Sep. 2008 |
| % of Completion |
10% |
| Consultant Architect |
M/s. Gherzi Eastern, Mumbai |
|
|
|
| |
| [5] |
Description Of Project
& Name Of Client |
Construction of Admin Bldg. for M/s. Bombay Rayon Fashions Ltd., Tarapur - Boisar |
| Value Rs. Lakhs |
2513* |
| Date Of Commencement |
Dec. 2007 |
| Scheduled Completion Date |
Sep. 2008 |
| % of Completion |
40% |
| Consultant Architect |
M/s. Gherzi Eastern, Mumbai |
|
|
|
| |
| [6] |
Description Of Project
& Name Of Client |
Construction of Residential Complex for M/s. Central Chinmaya Mission Trust., Pune.
|
| Value Rs. Lakhs |
850* |
| Date Of Commencement |
Aug. 2007 |
| Scheduled Completion Date |
May 2008 |
| % of Completion |
90% |
| Consultant Architect |
M/s. Group Seven, Mumbai.
|
|
|
|
| |
| [7] |
Description Of Project
& Name Of Client |
Construction of Mega Power Plant for M/s. China National Machinery And Equipment Import & Export Corporation, Kovaya - Amreli. |
| Value Rs. Lakhs |
2900* |
| Date Of Commencement |
Jun. 2006 |
| Scheduled Completion Date |
Aug. 2008 |
| % of Completion |
90% |
| Consultant Architect |
M/s. Development Consultant Pvt. Ltd., Mumbai. |
|
| |
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
| |
| [8] |
Description Of Project
& Name Of Client |
Construction of Factory Building for M/s. SKF Technologies (India) Pvt. Ltd., Bavla - Ahmedabad.
|
| Value Rs. Lakhs |
2511 |
| Date Of Commencement |
Mar. 2008 |
| Scheduled Completion Date |
Sept. 2008 |
| % of Completion |
10% |
| Consultant Architect |
M/s. Gherzi Eastern, Mumbai.
|
|
|
|
| [9] |
Description Of Project
& Name Of Client |
Construction of API & Pilot Plant for M/s. Unimark Remedies Ltd., Vapi
|
| Value Rs. Lakhs |
565* |
| Date Of Commencement |
Apr. 2008 |
| Scheduled Completion Date |
Sep. 2008 |
| % of Completion |
Just Started |
| Consultant Architect |
M/s. B. V. Ram Sharma & M/s. B. Mehtalia Consultants Pvt. Ltd., Ahmedabad |
|
| [10] |
Description Of Project
& Name Of Client |
Construction of Process House, Weaving and Godown for M/s. Alok Textiles, Vapi
|
| Value Rs. Lakhs |
2000* |
| Date Of Commencement |
Oct. 2007 |
| Scheduled Completion Date |
Oct. 2008 |
| % of Completion |
50% |
| Consultant Architect |
M/s. Gherzi Eastern, Mumbai. |
|
|
|
| [11] |
Description Of Project
& Name Of Client |
Construction of Process & Weaving for M/s. Mandhana Industries, Boisar
|
| Value Rs. Lakhs |
1711* |
| Date Of Commencement |
Feb. 2008 |
| Scheduled Completion Date |
Nov. 2008 |
| % of Completion |
10% |
| Consultant Architect |
M/s. Gherzi Eastern, Mumbai. |
|
| [12] |
Description Of Project
& Name Of Client |
Construction of Process & Embroidery Building for M/s. Dicitex Decor Pvt. Ltd., Boisar.
|
| Value Rs. Lakhs |
1500* |
| Date Of Commencement |
April 2008 |
| Scheduled Completion Date |
Dec. 2008 |
| % of Completion |
Just Started |
| Consultant Architect |
M/s. Pratap Parikh & Associates, New Delhi. |
| [13] |
Description Of Project
& Name Of Client |
Construction of Upgradation and Modernisation of Factory Building for M/s. Blossom Industries Ltd., Daman
|
| Value Rs. Lakhs |
469* |
| Date Of Commencement |
Nov. 2007 |
| Scheduled Completion Date |
Jun. 2008 |
| % of Completion |
80% |
| Consultant Architect |
M/s. Sanghvi & Associates, Mumbai. |
| [14] |
Description Of Project
& Name Of Client |
Construction of Factory Building for M/s. Bilag Industries, Vapi
|
| Value Rs. Lakhs |
500* |
| Date Of Commencement |
Apr. 2008 |
| Scheduled Completion Date |
Sep. 2008 |
| % of Completion |
Just Awarded |
| Consultant Architect |
M/s. B. Mehtalia & Co., Mumbai. |
|
|
|
|